The critical path is the chain of tasks with no room to slip. To calculate the critical path, run a forward pass to find the earliest the project can finish, then a backward pass to find how late each task can start without moving that finish. The tasks with zero total float form the critical path when the backward pass is anchored to the earliest finish. Microsoft’s page on managing the critical path explains how Project defines a critical task.

When printing and assembling planner inserts, the critical path might run through proof approval, batch printing, trimming, punching and assembly. Preparing the covers could take longer than any one of those tasks and still have time to spare. What matters is how long each linked sequence takes, and which sequence finishes last at the point where the work comes together.
The critical path calculation, from task list to finish date
List the tasks, durations and immediate predecessors. Set one finish condition, such as “all 30 planner sets checked and ready to pack”. Give each task an ID, record its duration and identify the tasks that must finish before it can start. Use elapsed minutes for a single production session and include time that blocks the next task. If a print run takes 35 minutes and the sheets need 10 more minutes before trimming, allow 45 minutes or record the wait separately. Don’t enter only the minutes someone spends at the printer.
Start with finish-to-start links: trimming follows printing because the trimmer needs printed sheets. Don’t link cover preparation to printing just because both follow proof approval. If more than one task can end the project, connect them to a single zero-duration finish milestone so the backward pass has one endpoint. For jobs with drying time or other waits between tasks, use a predecessor table with finish-to-start dependencies and lag to record exactly where each wait applies.
Run the forward pass to find the earliest finish. Start each task with no predecessor at elapsed minute 0. Enter its early start (ES) and add its duration to get its early finish (EF). For every other task, take the largest early finish among its immediate predecessors as its early start. Work from the start of the network towards the finish, calculating a row only after all its predecessors have an early finish.
ES = max(predecessor EF values)
EF = ES + durationIf punched inserts are ready at minute 120 and the labelled covers are ready at minute 85, assembly starts at 120. It can’t start at 85 because one input is missing, and it doesn’t start at 205 because the two streams of work overlap. The early finish of the last task or finish milestone is the earliest project finish under the current plan.
Run the backward pass to find the latest safe starts. Set the late finish (LF) of the final task or finish milestone equal to its early finish. Subtract duration to get late start (LS). Work back towards the first task. If a task has more than one immediate successor, use the smallest late start among those successors as its late finish. Taking the largest would protect only the successor that can wait longest.
LF = min(successor LS values)
LS = LF − durationIf proof approval releases two tasks with late starts at minutes 20 and 55, the proof must finish by minute 20. A late finish of 55 would leave the first task 35 minutes short. Use the earliest project finish for this first calculation, even if the customer’s collection time is later. That keeps the critical path calculation separate from any extra time allowed by the deadline.
Calculate total float and trace the linked tasks. Subtract early start from late start. You can check the result by subtracting early finish from late finish. The two calculations should agree for every task in this finish-to-start model.
Total float = LS − ES = LF − EFA task with zero total float has no room to slip without moving the planned finish, unless another part of the schedule changes to recover the time. Trace the zero-float tasks from the start to the finish using their dependency links. If two branches take equally long to reach the same join and both are on a controlling route to the finish, both can be critical. Don’t select one just to produce a single highlighted line.

Worked example: printing and assembling 30 planner insert sets
A small production team is printing 30 sets of weekly planner inserts. The batch stays together through printing, trimming and punching, and assembly starts only when all the inserts and labelled covers are ready. The proof includes a duplex alignment check and a test fit against the punch guide. Cover stock is already on hand, and a second operator can prepare covers while the first handles the insert batch.
The durations below are planning assumptions for this job, not production rates. Time is measured from a 09:00 start, with no breaks or extra waits in the model. The job ends when the assembled sets pass the final count and spot check.
| ID | Task | Duration (min) | Predecessors | ES | EF | LS | LF | Total float (min) |
|---|---|---|---|---|---|---|---|---|
| A | Print and approve the proof | 20 | None | 0 | 20 | 0 | 20 | 0 |
| B | Print the insert batch | 45 | A | 20 | 65 | 20 | 65 | 0 |
| C | Trim the inserts | 30 | B | 65 | 95 | 65 | 95 | 0 |
| D | Punch the inserts | 25 | C | 95 | 120 | 95 | 120 | 0 |
| E | Cut and prepare the covers | 50 | A | 20 | 70 | 55 | 105 | 35 |
| F | Apply labels to the covers | 15 | E | 70 | 85 | 105 | 120 | 35 |
| G | Assemble the sets | 35 | D, F | 120 | 155 | 120 | 155 | 0 |
| H | Count and spot-check the sets | 15 | G | 155 | 170 | 155 | 170 | 0 |
Forward pass: assembly waits for the punched inserts
The proof starts at minute 0 and finishes at 20. The insert batch then goes through printing, trimming and punching: B finishes at 20 + 45 = 65, C at 65 + 30 = 95, and D at 95 + 25 = 120. In parallel, the covers are prepared from minute 20 to 70 and labelled from 70 to 85.
Assembly takes the larger of 120 and 85 as its early start. It finishes at 120 + 35 = 155, and the final check adds 15 minutes. The earliest finish is minute 170, or 11:50. Adding all eight task durations would give 235 minutes, which would count the parallel cover work as if it happened after the insert work.
Backward pass: proof approval has two different limits
Set the final check’s late finish to 170. It must start by 170 − 15 = 155, so assembly must finish by 155 and start by 120. Both punching and labelling must finish by minute 120 because both feed assembly. Their own durations produce different late starts: punching must start by 95, but labelling can start as late as 105.
Keep moving back along each branch. On the insert side, trimming must finish by 95 and start by 65, so batch printing must finish by 65 and start by 20. On the cover side, preparation must finish by 105 and start by 55. Proof approval feeds both batch printing and cover preparation, so it takes the smaller limit, minute 20, as its late finish. Subtract the proof’s 20 minutes and its late start is 0.
Float check: 35 minutes on the cover branch is shared
The critical path is A → B → C → D → G → H. Its durations add up to 170 minutes, matching the forward pass. Cover preparation has 55 − 20 = 35 minutes of total float, and labelling has 105 − 70 = 35. That’s one shared allowance on a linked branch, not 70 minutes to spend.
Say cover preparation takes 70 minutes instead of 50. It now ends at minute 90 and pushes labelling to minute 105, but assembly can still start at 120. The cover branch has only 15 minutes left. There’s a distinction here between total float and free float: cover preparation originally had zero free float because delaying it immediately delays labelling. Labelling originally had 35 minutes of free float because it could finish that much later without moving the early start of assembly.
Fixes when the schedule doesn’t match the production workflow
Check the join and the split before correcting individual cells
If assembly shows an early start of 85, check the forward formula in row G. It needs the maximum of the punching and labelling early finishes. If proof approval shows a late finish of 55, check row A in the backward pass. It needs the minimum of the two successor late starts. These two rows catch errors that can spread through the rest of the table while leaving individual duration calculations looking right.
Also check how the worksheet treats time. In the example, minute 20 is both the end of the proof and the first possible start of batch printing. There’s no extra minute between them. If the plan uses calendar dates and no work takes place over the weekend, a Friday afternoon finish may release its successor on Monday morning instead. Use a working calendar rather than adding a fixed gap to each link.
For a recurring job scheduled in Excel, the PlanLane Gantt chart template can turn durations and dependencies into scheduled dates, skip weekends and holidays, and show the plan on a colour-coded timeline. Keep the elapsed-minute example as a reference when checking which tasks can run in parallel before moving the live schedule to dates.
Resolve shared equipment and staffing before promising a finish
The 11:50 finish assumes the cover operator can work from 09:20 while the insert batch runs. If both jobs need the same guillotine, check the overlap: cover preparation is planned to end at 10:10, but insert trimming is due to start at 10:05. If the cover cuts can safely pause, place them around the insert trim. If they can’t, choose which job gets the guillotine first and recalculate. Don’t treat the conflict as proof that covers physically depend on trimmed inserts.
The same check applies if one person must supervise printing and cut covers. A dependency calculation won’t allocate that person to one job instead of the other. Use a resource levelling workflow for tasks that need the same person to settle the order, then rerun the passes on the feasible schedule.
Model early batches only if the bench can accept them
The example uses one print task and one trim task because all 30 sets move together. If the first 10 sets can be trimmed while the remaining 20 are still printing, split the job into numbered batches and link each trim task to its own print task. Keep any final count or packing milestone linked to all batches required for handover.
Before counting the time saving, check the physical process. If pages come off the printer grouped by design rather than collated by set, the first pile may not contain 10 complete sets. And if two batches need the trimmer at the same time, add the actual trim sequence. The new critical path may run through the queue at the trimmer rather than through the full printing run.
Recalculate after overruns and keep the deadline separate
If cover preparation takes 90 minutes instead of 50, labelled covers finish at minute 125. Assembly now waits for covers rather than inserts, and the project finishes at minute 175. The critical path has switched branches. For schedules that are revised frequently, the Projectory Gantt chart planner app reschedules linked tasks when you move a task, shows the critical path and works offline.
Treat a fixed collection time as a separate test. An 11:40 handover is minute 160, ten minutes earlier than the original calculated finish. If you anchor a second backward pass to 160, the original controlling tasks show −10 minutes of total float. That figure measures the recovery needed; it doesn’t make the earlier handover feasible.
Before committing to a recovery plan, test it against the branch that would take over. Cutting cover preparation by 10 minutes saves nothing on the original schedule because assembly is waiting for punching. Cutting 10 verified minutes from the insert sequence brings assembly forward from minute 120 to 110, still later than the covers at 85, and makes the 11:40 handover possible. If the proposed saving depends on untested printer settings or skipping the proof check, retain the calculated finish and renegotiate collection instead.