A predecessor table lists what has to finish before each task can start, plus any waiting time. To build a predecessor table, give each task an ID and a duration, then list the tasks that must finish before it can start. For every finish-to-start link, record any required wait as lag, add it to the predecessor’s finish, and use the latest result to set the successor’s earliest start. Microsoft Project’s guide to lead and lag time follows the same logic.

For printing and assembling planner inserts, that means separating three things: the time it takes to print the batch, the time printed sheets must rest before handling, and the time it takes to trim and punch them. Printing and trimming are tasks. A required rest with no work during it is lag. Treating all three as one duration hides the point at which a delay will affect assembly.
Build the predecessor table in five steps
List tasks with a clear finish condition.
Start with the hand-offs that release the next piece of work. ‘Print inserts’ is useful if it means the full batch has been printed and counted. ‘Work on inserts’ could mean anything from checking the PDF to sorting the last set, so it’s no help when deciding when trimming can start.
In the predecessor table, give each task a stable ID such as
AorPRINT. Include columns for Task ID, Task, Duration, Predecessor link(s), Earliest start and Earliest finish. If the workbook will be maintained by more than one person, add a note column for assumptions such as ‘proof signed off’ or ‘one working day of rest before trimming’. Keep IDs in the predecessor table stable when you rename or reorder tasks.Set the task size to match the way the batch moves. If all 40 sets go to the punch together, one print task and one trim-and-punch task can be enough. If the first 10 sets can move ahead while the next 30 are still printing, model the batches separately. A link from ‘Print all 40 sets’ to ‘Punch batch one’ would hold up work that could already begin.
Add finish-to-start links only where a hand-off requires them.
For each task, identify what must already be complete. A signed-off duplex proof can release the main print run, so if the proof is task
B, the print row getsB FS+0.FSmeans finish-to-start. With zero lag, the successor is eligible to start as soon as the predecessor finishes, subject to the working calendar and any other incoming links. A task with no predecessor can start at the project start unless a separate restriction applies.If collation needs both punched inserts and prepared dividers, put both links on the collation row. Don’t make divider preparation wait for printing just because it appears lower in the predecessor table. Equally, don’t list the proof again as a direct predecessor of collation when the proof already controls printing and printing controls the punched inserts. Record the immediate hand-offs so the reason for each link stays visible.
Put lag on the link and specify which clock it uses.
Write
C FS+1 wdto mean ‘start at least one working day after task C finishes’. Store the predecessor ID, link type, lag value and lag unit in separate predecessor table columns if a spreadsheet will calculate the dates. The compact notation is useful for inspection, but a formula shouldn’t have to extract a number and a unit from a label.Use lag when time must pass without a separate job to assign. If staff need to inspect the sheets after the wait, that inspection is a task with a duration and a finish condition. If the lag in the predecessor table is 24 hours of elapsed time, don’t substitute one working day. On a Monday to Friday calendar, 24 hours after a Thursday evening finish is Friday evening; one working day of lag consumes Friday’s working time. Check when the successor can actually start once its own working calendar is applied.
Record the reason for any positive lag. ‘One working day before trimming, based on the shop’s checks for this batch’ is a scheduling assumption someone can verify. ‘Add a day just in case’ is a buffer, and it shouldn’t be hidden inside a physical hand-off.
Calculate earliest starts using the latest incoming release.
For a simple first pass, keep every duration and lag in working days and calculate with offsets from the project start. Set the first available boundary to
0. A one-day task starting at0finishes at boundary1. If its successor has zero lag, it can start at1; if the link has one day of lag, the successor can start at2. The finish boundary marks the end of the time consumed, not another day of work.Work through the predecessor table from predecessors to successors. Use earliest finish = earliest start + duration for each task. For each incoming finish-to-start link, calculate release = predecessor’s earliest finish + lag. The successor’s earliest start is the maximum of its incoming releases. Don’t add the releases together: if the dividers are ready at
4and the punched inserts at6, collation starts at6, not10.In Excel, a small manual predecessor table might have the print finish in
F5and its lag inG6, so the next task’s earliest start is=F5+G6. For two incoming links, use the pattern=MAX(finish1+lag1,finish2+lag2), replacing those names with the relevant cells. If tasks are often inserted or moved, use a separate predecessor table with one row per predecessor and successor pair, and look up finishes by task ID rather than relying on fixed row positions.If the schedule is maintained in Excel and needs dated views as well as dependency records, the PlanLane Gantt chart template calculates dates from tasks, durations and dependencies, skips weekends and holidays, and draws a colour-coded timeline. Before moving a manual schedule into a template, test the print-to-trim link against a weekend so the displayed date can be checked against the agreed lag rule.
Check which links control the delivery date.
Start the backward pass at the earliest project finish unless there’s a separate deadline to assess. For a predecessor with an outgoing finish-to-start link, subtract the link’s lag from the successor’s latest start to find the latest finish that link permits. If the predecessor has several successors, take the minimum of those limits. Subtract the predecessor’s duration to get its latest start.
Total float is latest start minus earliest start. With the backward pass anchored to the earliest finish, a task with zero total float can’t slip without moving that finish, unless something else changes. A lag can sit on the controlling path even though nobody is working during it. For a larger network with several branches feeding the same milestone, use the full forward and backward pass for critical path calculations.
If the production schedule is revised by moving tasks on a timeline, the offline Projectory Gantt chart planner app reschedules linked tasks when a task is moved and displays the critical path. After moving the print run, check both the new trimming date and the collation hand-off: the branch that controls assembly can change after a revision.

Worked example: Print and assemble 40 sets of planner inserts
A print room has 40 sets of A5 planner inserts to print, trim, punch and pack. The dividers can be prepared once the page dimensions and punch pattern are confirmed. This example assumes there’s separate capacity for divider preparation and printing, so those tasks can overlap. The shop has also scheduled one full working day of rest between printing and trimming for this batch. That’s an example production constraint, not a drying recommendation for other paper or printers.
The project starts on Monday 2 March 2026. The working week is Monday to Friday, with no holidays in the period. The durations represent reserved production slots, not continuous hands-on time. That’s why checking a proof occupies a day in the schedule even if the printing and inspection take much less.
| ID | Task and finish condition | Duration (working days) | Predecessor links | Earliest start | Earliest finish |
|---|---|---|---|---|---|
| A | Confirm A5 layout and punch pattern | 1 | None | 0 | 1 |
| B | Print and approve a duplex proof | 1 | A FS+0 | 1 | 2 |
| C | Print and count all 40 sets | 2 | B FS+0 | 2 | 4 |
| D | Prepare and count matching dividers | 3 | A FS+0 | 1 | 4 |
| E | Trim and punch all printed sheets | 1 | C FS+1 wd | 5 | 6 |
| F | Collate inserts and dividers into 40 sets | 1 | D FS+0, E FS+0 | 6 | 7 |
| G | Check page order and pack all sets | 1 | F FS+0 | 7 | 8 |
Convert the offsets into production dates
Task A takes Monday, and the proof takes Tuesday. Printing occupies Wednesday and Thursday and finishes at boundary 4, after Thursday’s work. The one-day lag occupies Friday. The next working boundary is 5, so trimming and punching take place on Monday 9 March, not Friday 6 March.
The dividers finish at 4, while the punched sheets finish at 6. Collation uses MAX(4, 6) and starts at 6, on Tuesday 10 March. Checking and packing take Wednesday 11 March. Boundary 8 marks completion at the end of Wednesday’s slot. If a spreadsheet shows boundary 8 as the start of Thursday 12 March, don’t report Thursday as a day spent packing. Label the column as a boundary or report the last occupied workday separately.
Run the backward pass and test a delay
Set the latest finish of packing to 8. Packing must start by 7, collation by 6, and trimming by 5. For printing, subtract the one-day lag from trimming’s latest start: 5 − 1 = 4. Printing must finish by 4, so its latest start is 2. Carrying that calculation back through the proof and layout gives the controlling path A → B → C → E → F → G, including the rest period between C and E.
Divider preparation only needs to finish by 6, when collation starts. Its three-day duration gives a latest start of 3, two days later than its earliest start of 1. It has two working days of total float and, in this schedule, two days of free float as well: it can finish at 6 without shifting collation’s earliest start. Those two measures can differ when there are further hand-offs; use the total float and free float calculation for a delayed task to distinguish them.
Test the predecessor table with a proof correction that moves printing one working day later. Printing now takes Thursday and Friday, the sheets rest on Monday, and trimming moves to Tuesday. Collation moves to Wednesday and packing to Thursday 12 March, and the predecessor table updates both dates. By contrast, a one-day delay to divider preparation alone moves its finish from 4 to 5, which is still before collation’s controlling release at 6.
Fix the errors that move the wrong tasks
Trimming starts on Friday instead of Monday
Check the calendar and the meaning of the finish field before changing the lag. If ‘Thursday’ means the print run finishes at the end of Thursday, a full working day of lag occupies Friday. Trimming begins on Monday. If a dated workbook adds one to Thursday and uses the result as Friday’s start, it has mixed a last-workday label with a start boundary. Recalculate using offsets or explicit start and finish times. Repeat the check with a Monday holiday: trimming should then move to Tuesday under the working-day rule.
Collation starts after only one of its inputs is ready
Check that the collation row contains both predecessors and takes the maximum of their releases. If a divider stock delay moves D’s finish from 4 to 7, the correct result becomes MAX(7, 6) = 7. The controlling branch changes even though printing and trimming are still on schedule. A formula that points only to the trim-and-punch row will miss that change. Also check for circular references: adding collation as a predecessor of divider preparation would make each task wait for the other.
The table overlaps work that one operator must do
The example allows divider preparation to overlap the proof and print run. If the same operator must actively run the printer and prepare the dividers, those dates may be impossible even though the dependency arithmetic is correct. Confirm how much operator time each slot actually needs, then level the schedule when two tasks need the same person. Don’t add a permanent print-to-divider dependency unless the dividers genuinely need an output from printing. A staffing conflict can disappear with a second operator; a production hand-off cannot.
The next batch could start sooner than the table allows
Check whether the lag applies to the last sheet off the printer or to each separately handled stack. If the first 20 sets are tracked apart from the second 20 and can be released independently, give each batch its own print and trim tasks and apply the rest lag to each pair. Keep both trim tasks as predecessors of final collation if nothing can be collated until all 40 sets are ready. Only split the batch if someone can identify which stack completed its wait; otherwise, keep the full-batch hand-off.
Before publishing the production dates, move the main print finish one working day later in a copy of the table. If the batch rest, trimming, collation and packing shift while divider preparation stays put, the print branch is behaving as intended. Then move the divider finish past the punched-sheet release. Collation should follow the dividers instead. Run both checks before using the table to commit to a packing date.