Total float and free float tell you two different things when a task runs late. Calculate total float by subtracting a task’s earliest finish from its latest finish. Calculate free float by finding the smallest gap between that task’s earliest finish, plus any link lag, and the earliest start of each immediate successor. Microsoft’s critical path guide calls total float and free float total slack and free slack, but the idea is the same.

If a print run slips by three working days and had two days of free float but four days of total float, the next operation may move without changing the project finish. The original total float and free float explain what the delay consumed. The recalculated total float and free float tell you how much room is left. Keep those figures separate when deciding whether to rebook the cutting slot, move the assembly shift or change the dispatch date.
Total float and free float workflow for a delayed task
Choose the schedule you’re measuring against. Keep a copy of the accepted schedule before entering the delay. Record its project finish, the delayed task’s early finish and the early starts of its immediate successors. If printing was due to finish at the end of Tuesday but is now forecast to finish at the end of Thursday, measure that change on the working calendar. If Tuesday was already a revised date, label it as the last accepted forecast rather than the original baseline.
Check the links that carry the delay. For a finish-to-start link, the next task cannot start until its predecessor finishes and any lag has passed. If printed sheets need one day to dry before trimming, include that day in the print-to-trim link. If trimming also needs a cutting guide, its early start depends on both inputs. A predecessor table with finish-to-start links and lag makes it easier to spot which requirement controls the start. Include the work that makes the batch ready to dispatch, such as final inspection and packing, so the finish you’re protecting is the right one.
Calculate early dates with a forward pass. Start at time zero. For each task, set its earliest start (ES) to the largest of its predecessors’ earliest finishes plus the relevant link lags. Add the task duration to get its earliest finish (EF). For a manual calculation, use working-day boundaries: a two-day task starting at boundary 1 finishes at boundary 3, and a successor with no lag can start at boundary 3. Don’t add another day for the handover. If the task is already in progress, preserve its actual start and forecast its finish from the remaining work as of the status date.
Calculate late dates with a backward pass, because you need them for total float and free float. Set the final milestone’s latest finish to the date you want to test. Use the finish from the forward pass to measure against the schedule’s own earliest completion, or use a required dispatch date to measure against a commitment. Work backwards. For each finish-to-start link, subtract its lag from the successor’s latest start.
The smallest result across all immediate successors is the task’s latest finish (LF). Subtract the duration to get its latest start (LS). The forward and backward pass method for calculating the critical path shows how these dates fit across the full network.
Calculate both floats and identify what each one protects.
- Total float = LF − EF. For a task with fixed duration on a single working calendar, this also equals LS − ES. If printing can finish as late as day 7 and is scheduled to finish on day 3, it has four working days of total float against the chosen finish date.
- Free float = the smallest value of successor ES − task EF − link lag. If trimming is set to start on day 6, printing finishes on day 3 and the sheets need one day to dry, free float on that link is two days. That’s why total float and free float often differ. If a separate proof check can absorb only one day of printing delay, the printing task’s free float is one day. Use the tightest link, not the first row in the schedule.
Enter the delay and run both passes again. Enter the revised duration, remaining work or release date that caused the slip. Don’t move the successor by hand before running the calculation. Compare the old and new finish dates for the delayed task, the affected successors and the final milestone. A three-day slip against two days of original free float suggests a one-day movement in the tightest successor if nothing else changes. Once several tasks slip, calendars differ or a new dependency is in play, the before-and-after dates are more reliable than subtracting the delay from the old float.
For a recurring planner insert workflow managed in Excel, the PlanLane Excel Gantt chart template calculates dates from durations and dependencies and skips weekends and holidays. Save a dated copy before changing the print forecast so the original cutting and packing dates stay available for comparison.

Worked example: a three-day delay in printing planner inserts
A batch of weekly planner inserts needs duplex printing, trimming and hole punching before assembly. Covers are prepared in parallel. The printed sheets need one working day to dry, modelled as lag in this schedule. All work uses the same calendar, and no two tasks are competing for the same person or machine.
Build the original dates
The forward and backward pass results, with total float and free float, are below. Numbers are working-day boundaries rather than calendar dates. For example, printing from day 1 to day 3 occupies two working days. The original project finish is day 14, which is also the committed dispatch point for this batch.
| Task | Predecessor | Duration | ES | EF | LS | LF |
|---|---|---|---|---|---|---|
| Approve proof | None | 1 | 0 | 1 | 0 | 1 |
| Print inserts | Approve proof | 2 | 1 | 3 | 5 | 7 |
| Set up cutting guide | Approve proof | 5 | 1 | 6 | 3 | 8 |
| Trim inserts | Print inserts, plus 1 day of lag; cutting guide ready | 2 | 6 | 8 | 8 | 10 |
| Punch inserts | Trim inserts | 1 | 8 | 9 | 10 | 11 |
| Prepare covers | Approve proof | 10 | 1 | 11 | 1 | 11 |
| Assemble sets | Punch inserts; prepare covers | 2 | 11 | 13 | 11 | 13 |
| Pack for dispatch | Assemble sets | 1 | 13 | 14 | 13 | 14 |
In the forward pass, printing finishes on day 3 and the sheets are ready to trim on day 4. The cutting guide isn’t ready until day 6, so trimming starts on day 6. Punching finishes on day 9. The covers aren’t ready until day 11, which sets the assembly start. Packing then finishes on day 14.
In the backward pass, packing must start by day 13, so assembly must start by day 11. Punching must finish by day 11 and start by day 10. That gives trimming a latest start of day 8. Allow one day for drying and the latest printing finish is day 7.
Printing has four days of total float: day 7 minus day 3. It has two days of free float: day 6 minus day 3 minus one day of drying. The first two days come from waiting for the cutting guide. The other two are available farther down the branch, before assembly needs the punched sheets.
Update the print forecast and measure the effect
Say a printer fault adds three working days to the print operation. The print start stays on day 1 and the forecast finish moves from day 3 to day 6. Drying moves the sheet-ready date to day 7. The cutting guide is still ready on day 6, but it no longer controls trimming.
Trimming now runs from day 7 to day 9. Punching finishes on day 10, one day later than planned. Covers still finish on day 11, so assembly and packing hold their dates. The production change to communicate is a one-day move to trimming and punching, not a three-day move to dispatch.
The backward pass still puts the latest printing finish on day 7. Against that date, the updated print finish on day 6 leaves one day of total float. Updated free float is zero: day 7 for the new trimming start, minus day 6 for the print finish, minus one day for drying. Another one-day printing slip would move trimming again, but the punched inserts would still reach assembly on day 11.
If printing instead finishes on day 8, trimming starts on day 9, punching finishes on day 12 and packing finishes on day 15. Against committed dispatch on day 14, printing has negative one day of total float: its latest finish is day 7 and its forecast finish is day 8. A backward pass anchored to the new day 15 finish would show zero total float and free float on the now-critical print branch. The figures answer different questions: one measures the dispatch shortfall; the other identifies the work controlling the current forecast.
Fix the errors that give misleading float figures
Use working time from the schedule, not calendar subtraction
A Friday finish followed by a Monday start can have zero free float on a Monday-to-Friday calendar: the two dates meet at the same working-time boundary. If a drying lag runs across the weekend in elapsed time, it behaves differently from a lag counted only on working days. Check the task and lag calendars before applying a hand calculation, especially if the printer can run on Saturday but the assembly team doesn’t work weekends.
Check every successor, including handovers outside production
A printing task can feed trimming and a same-day sample inspection. If inspection can wait only one working day while trimming can wait two, printing has one day of free float. A scheduled inspection needn’t control dispatch to matter. If it has its own fixed booking, record that constraint rather than assuming the normal finish-to-start link captures it.
Also check the link type before you calculate total float and free float. A start-to-start link constrains a successor’s start from the predecessor’s start, not its finish. If packing can start after the first sets are assembled, defining separate batch tasks may describe the handover more accurately than applying the full-batch finish-to-start formula to overlapping work.
Don’t allocate the same float twice
Of total float and free float, only total float is shared along a branch. In the example, printing could finish on day 7 and still protect day 14 dispatch, but that would push trimming to its latest start of day 8. The trim operation wouldn’t also have its original two days of total float available. Update the connected tasks before approving a second delay, even if the original schedule shows spare time in both rows.
Test printer, cutter and staffing capacity separately
A dependency calculation can place cover preparation and cutting-guide setup in parallel. If both need the same operator for the same shift, the dates may be impossible even when the network shows positive float. Level the schedule when two tasks need the same person before treating those dates as production slots. A cutter booked for another order can turn a one-day move into a wait until the next available shift.
When testing several changes to linked dates, Projectory’s Gantt chart planner lets you drag a task on the timeline, reschedules linked tasks and shows the critical path. Keep the committed dispatch date in your status record so a change to the forecast finish doesn’t erase the comparison.
Forecast the remaining work instead of moving actual dates
If half the inserts have already printed, leave the actual start in place and recalculate total float and free float from there. Estimate how much printing remains and when the printer will be available. A task that has already started can’t use start float to change its past, so use its forecast finish for the finish-based check. If the first half can go to trimming while the second half is still printing, split the work into two linked batches only if the cutter and operator can take that first handover.
Don’t shorten a drying or inspection allowance simply to make a date fit. If a batch needs one working day to dry, protect that time. If recovery is needed, test a specific change, such as starting the approved portion sooner or moving packing to a later shift that still makes the carrier collection. Run the schedule again to see which change actually recovers the lost day.
For the next production update, record the revised print finish, the first successor that moves and the forecast dispatch date beside the commitment. In the three-day delay example, the useful instruction is: move trimming and punching by one working day, keep assembly and dispatch in place, and flag any further printing slip because only one day of dispatch margin remains.